CNBM Awarded the PAC of NRCC Tank #5 Project

 

On January 24th , 2016, NRCC 10000 m3 HFO Tank #5 EPC project, constructed by CNBM International Engineering, Co., Ltd, received the Provisional Acceptance Certificate from the owner.

 

This contract was signed in May, 2016 in Saudi Arabia and officially started on June 2nd, 2014. The civil & installation construction tender has been completed on June 16th, 2014, and the subcontract has been signed with the construction company. The first batch of construction personnel entered the site on August 8th, 2014 and the site handover has been done after then. CNBM International Engineering, Co., Ltd has completed the civil construction, installation work and successfully oiling on July 7th, 2015; the single commissioning has been done on July 17th, 2015.

 

From July 19th, 2015 to November 28th, 2015,  the  linkage debugging has been suspended since the heavy oil supply can't meet the minimum requirements of equipment linkage operation (the height of the heavy oil is 3.5m ). The linkage debugging has been restarted on November 29th, 2015 and this work has been finished on December 25th, 2015. The PAC has been issued on January 24th , 2016.

 

Based on company leaders careful guidance, clearly contract clauses, unified execution team and  feasible project schedule, this project department has successfully fulfilled all the contractual obligations by excellent technology and responsible attitude. The running-well oil supply system was highly appraised by the owner, and earned reputation for CNBM International Engineering Co., Ltd in Saudi Arabia and Middle East market once again.

 

63c06da850c5ed5c7def889bf1cfd85a.png

 

48c369151d997c268caa04b48faea6e0.png